UT Health Hospital

Propel Prefabrication finds creative way to work around labor shortage while still delivering top-quality products and services.

Challenge

An industry-wide labor shortage threatens to negatively impact the project timeline. There needs to be a way to complete routine, non-critical electrical tasks so the project stays on schedule.

Solution

Our prefab shop completes work typically assigned to more skilled labor by utilizing apprentices working under the watchful eyes of a Master Electrician and our strict QC program. This solution supports the project while also helping alleviate the ongoing labor shortage, since graduating apprentices often transition to serve as full-time, certified FSG technicians.
Project Type
Electrical
Contract Amount
$478,000.00